2847 Oakwood Dr, Austin TX
Project Progress
Plan
Prep
3
Build4
DoneBudget
$29,250 spent$45,000 budget
65% of budget used - $15,750 remaining
Team5 members
MT
Mike Torresowner - Torres Construction LLC
SC
Sarah Chenclient
RV
Rico Vasquezsubcontractor - Vasquez Electric
MS
Maria Santossubcontractor - Santos Plumbing Co
TB
Tom Bradleysupplier - BuildRight Materials
Phases
Planning & DesignCompleted
Started Dec 1 - Ended Dec 20100
Pre-ConstructionCompleted
Started Dec 21 - Ended Jan 15100
ConstructionIn Progress
Started Jan 1665
Completion & HandoffNot Started
0
Recent Messages
View AllMike Torres1 day ago
Cabinet install is looking great. Should be done by Thursday. I'll get with Rico about adding a third pendant location - shouldn't be a big deal since the island wiring is already in.
Sarah Chen1 day ago
I was looking at pendant lights for over the island - maybe 3 instead of 2? I'll send you some photos of what I'm thinking.
Mike Torres1 day ago
Yes, we have some flexibility before Rico comes back for finals. What are you thinking?