Good morning Sarah! Demo starts today. We've got the dust barriers up and everything is prepped. Should take about 3 days.
Exciting! We set up the temporary kitchen in the garage like you suggested. Please let us know if you need anything.
Demo day 1 progress - old cabinets out
Wow, it looks so different already! Can't wait to see the new layout take shape.
Rico is here for the electrical rough-in. He's running new 20-amp circuits for the island and upgrading the lighting wiring.
Hey Sarah, Mike asked me to loop in here. I'm adding dedicated circuits for your appliances - dishwasher, disposal, and microwave will each have their own. Much safer than the old setup.
That sounds great Rico, thank you! The old kitchen used to trip the breaker constantly.
Plumbing rough-in complete! Moved the sink line to the island location as planned. Everything is pressure-tested and ready for inspection.
Great news - both rough-in inspections passed! Flooring goes in next week.
LVP flooring is in - looking sharp!
Oh I love the walnut color! It's even better than the sample.
Cabinets arrived today from BuildRight. Starting install first thing tomorrow morning.
Heads up Mike - the countertop slabs shipped today. Should arrive by the 26th. I'll send tracking.
Perfect timing Tom, thanks. We'll be ready for template once the lowers are set.
Upper cabinets are in! Shaker whites looking clean.
They look amazing Mike!! Quick question - can we still adjust the lighting fixture placement before electrical final?
Yes, we have some flexibility before Rico comes back for finals. What are you thinking?
I was looking at pendant lights for over the island - maybe 3 instead of 2? I'll send you some photos of what I'm thinking.
Cabinet install is looking great. Should be done by Thursday. I'll get with Rico about adding a third pendant location - shouldn't be a big deal since the island wiring is already in.