65
Construction PhaseIn Progress
65%
Budget Monitor
$29,250 spent$45,000 budget
65% of budget used - $15,750 remaining
Demolition$3,200 / $3,200
Cabinets$12,500 / $12,500
Countertops$3,400 / $6,800
Electrical$4,500 / $4,500
Plumbing$3,800 / $3,800
Flooring$1,850 / $4,200
Backsplash$0 / $2,800
Painting$0 / $1,800
Fixtures$0 / $3,400
Permits$2,000 / $2,000
Task Board
In Progress (1)
Install lower cabinetsMike Torres
To Do (7)
Template countertopsStone World
Install countertopsStone World
Install backsplashMike Torres
Final electrical hookupsRico Vasquez
Final plumbing connectionsMaria Santos
Paint touch-upsMike Torres
Install hardware & fixturesMike Torres
Done (4)
Demo completeMike Torres
Rough-in electricalRico Vasquez
Rough-in plumbingMaria Santos
Install flooringMike Torres
Daily Log
Tuesday, Feb 24Mike Torres
Cabinet installation Day 3 - upper cabinets complete, starting lowers
Monday, Feb 23Mike Torres
Cabinet installation Day 2 - wall prep and uppers going in
Sunday, Feb 22Mike Torres
Cabinet installation Day 1 - delivery confirmed, layout marked
Friday, Feb 20Mike Torres
Flooring 90% complete, transition strips installed