Planning & Design

Johnson Kitchen Remodel

100
Planning & DesignCompleted

Client Selections

Cabinet StyleShaker White
Approved
Countertop MaterialQuartz - Calacatta
Approved
Backsplash TileSubway - Matte White
Approved
FlooringLVP - Walnut
Approved
Sink & FaucetKraus Undermount + Delta
Approved
Lighting FixturesPending final pick
Selected

Estimate Summary

Demolition & DisposalLabor
$3,200
Cabinets (supply + install)Materials
$12,500
Countertops (quartz)Materials
$6,800
Electrical workSubcontractor
$4,500
PlumbingSubcontractor
$3,800
Flooring (LVP)Materials
$4,200
Backsplash tile + installMaterials
$2,800
PaintingLabor
$1,800
Fixtures & hardwareMaterials
$3,400
Permits & feesAdmin
$2,000
Total Estimate$45,000

Key Milestones

Design approvalDec 15, 2025
Permits submittedDec 20, 2025
Demo completeJan 20, 2026
Rough-in completeFeb 5, 2026
Cabinets installedFeb 28, 2026
Final walkthroughMar 15, 2026