Pre-ConstructionCompleted
Site Prep Checklist
Kitchen contents cleared by client
Dust barriers installed
Temporary kitchen setup for client
Utility shutoffs verified
Material Orders
Shaker White Cabinets (full set)
DeliveredBuildRight Materials--1 set
Expected: Jan 28Quartz Countertop Slabs
ShippedStone World--2 slabs
Expected: Feb 26LVP Flooring - Walnut
DeliveredBuildRight Materials--380 sq ft
Expected: Jan 25Subway Tile - Matte White
OrderedBuildRight Materials--45 sq ft
Expected: Mar 1Delta Faucet + Kraus Sink
ShippedFerguson--1 each
Expected: Feb 27Subcontractor Schedule
Rico Vasquez - ElectricalJan 25 - Feb 5
CompletedMaria Santos - PlumbingJan 27 - Feb 7
CompletedRico Vasquez - Electrical (Final)Mar 5 - Mar 8
ScheduledMaria Santos - Plumbing (Final)Mar 5 - Mar 7
ScheduledPermits
Building PermitSubmitted Dec 20, 2025
ApprovedElectrical PermitSubmitted Dec 22, 2025
ApprovedPlumbing PermitSubmitted Dec 22, 2025
Approved